- For all Projects
PMO > Projects > Costs - SPI column (Schedule Performance Index) on far right hand side. - For all Schedules in a single Project:
Project > Schedules List > Costs - SPI column (Schedule Performance Index) on far right hand side.
- For all Tasks in a single Schedule
Project > Schedules > Schedule Detail > Costs
Click on the arrows to left of Name to expand to drill down to Task level
- Project Portfolio Summary report widget for Company Dashboards
This can be grouped by SPI (Schedule Performance Index) or SVI (Schedule Variance Index)
SPI = EV ÷ PV
SVI = EV - PV
- Project Progress report widget for Company or Project Dashboards
With the view set to show effort and this can show you SPI - Project Comparison report widget for Company Dashboards
The Data table view can include SPI traffic lights or you can compare EV to PV - If using BI there may be the option to include this in your reporting.
SPI Colour Coding: