The Process tab of a Deliverable shows you the Process for that Deliverable, as configured in the Blueprint.

The Tabular display shows you basic information about the Process that was configured for the Deliverable as follows:
- Name - Name of the Task
- Predecessors - Show any Dependencies within the Process
- Mandatory - Has the Task been marked as Mandatory
- Status - Is the Task Planned, in the Backlog, in Progress, Complete
- Health - Is the task on schedule or Delayed
- Schedule - Which schedule is the Deliverable Planned in
- Start Date - Of the Task
- End Date - Of the Task
- Condition - Of the Task
- Responsible - The user Responsible / generic profile for the Task
By selecting a Task (the row will highlight yellow) and clicking View you can see the Task Details > Overview tab.
You can Modify Dependencies by Double Clicking in cells under the Predecessors heading and adding the Line Numbers.
You can Add or Remove Tasks from the Process (as long as the Deliverable is not already planned in a schedule) using the + and - icons on the far right hand side.
You can also Export this view into your preferred format (CSV, PDF or Excel) using the button on the top right.