28th September 2018
Enhancement Item
ISSUE-1588 – Resource Custom Fields – Company Preferences menu
ISSUE-1594 - Structure folder lay-out of Project Plan view and Schedule List
ISSUE-1595 - Resource Custom Fields – Validation on Mandatory Fields
ISSUE-1596 – Resource Custom Fields – Filters within Workload
ISSUE-1597 – Assigning resources from the Workload
ISSUE-1609 - Schedules - Restrict the visibility of Schedules in the Plan View
ISSUE-1610 – Schedules - Add a colour code
ISSUE-1611 – Schedules - Making dependencies visible
ISSUE-1621 - Add progress planned task in pop-up + info from My Assignments
ISSUE-1622 – Resource Custom Fields – add to Data Warehouse
ISSUE-1624 - Add order of schedules within the grouping structure to Data Warehouse
Bug Item
ISSUE-1617 - Overwrite task time logs by moving the progress of the task from the Gantt (BAC).
ISSUE-1623 – Error loading Users due to Profile Changes