We are pleased to announce the latest version of Hydra is now available in Staging.
The list of bugs and enhancements is as follows:
Enhancements
[ISSUE-601] - Configure the parameters for the critical path
[ISSUE-1423] - Include the creator of a deliverable in the Data Warehouse
[ISSUE-1491] - Set Admin times to be Calendar exceptions
[ISSUE-1515] - HEnable API service for Administrative Times
Bugs
[ISSUE-94] - The title of Finances is not appearing marked with asterisk, when the information of finances is under edition.
[ISSUE-235] - Category of a material changes when other fields are modified
[ISSUE-450] - Timesheet report - Core update to fix multiple issues
[ISSUE-1100] - Remove the automatic configuration of critical path
[ISSUE-1124] - remove the option to add administrative times from project timesheets
[ISSUE-1262] - Inconsistent Task Numbering between Gantt and Progress Views
[ISSUE-1307] - error updating an administrative timelog
[ISSUE-1332] - Error tagging a document
[ISSUE-1444] - adding a second document to a deliverable does not show
[ISSUE-1446] - Error with Custom fields (List and String)
[ISSUE-1458] - Add SEK to Data Warehouse
[ISSUE-1469] - Editing a Project Alias - Alias is shown in grey so it looks like it can't be edited
[ISSUE-1471] - Planned progress S curve point appears to show the wrong day
[ISSUE-1472] - Add Condition to the changelogs
[ISSUE-1473] - Add the date of a condition change to the DB
[ISSUE-1493] - Tasks of 1300 days duration are allowed
[ISSUE-1501] - Cannot read property 'isVisible' of undefined Gantt
[ISSUE-1502] - Cannot read property 'getSuccessors' of null
[ISSUE-1507] - Exporting a schedul the progress of Activities is 0
[ISSUE-1508] - Error with Undo in the Gantt
[ISSUE-1509] - Remove deprecated Critical Path Code
[ISSUE-1511] - Error copying dates in the Gantt
[ISSUE-1512] - Error replacing resources in Gantt
[ISSUE-1514] - Error "Intl no está definido" on opening a gantt in an old browser
[ISSUE-1518] - Error Planning a deliverable in the Gantt
[ISSUE-1524] - Unscheduled events not showing in timesheet reports
[ISSUE-1526] - Error generating a timesheet report based on a saved report
[ISSUE-1532] - Inconsistent view of company profile in timesheet report